HALIFAX — Nov. 17, 2026 — The Halifax Select Board last Tuesday voted unanimously to have town counsel Brooks & DeRensis work on a temporary moratorium tied to the state’s new consolidated permitting process for small clean energy facilities, and to draft a possible bylaw for a special or annual town meeting. The board also accepted wage and personnel changes for fiscal 2026 through 2028.
The Full Story
Clean energy siting. Counsel from Brooks & DeRensis briefed the board by Zoom on the new state process, which lets developers of small clean energy projects seek a single consolidated local permit in place of separate approvals. The board was told the process covers solar, wind and anaerobic digestion facilities with capacities of less than 25 megawatts, energy storage of less than 100 megawatt hours and related transmission and distribution infrastructure.
Under the process as described, every local board reviews its part at the same time, and the town must issue one final decision within 12 months of receiving a complete application. If the town misses that deadline, there is a constructive approval. A denial by any one board makes the whole permit deniable, and appeals go to the director of the Facilities Siting Division at the state Department of Public Utilities rather than to a local board. Towns have had to start accepting these applications since Oct. 1, and Halifax has not received one.
Jonathan Selig said battery storage and biogas would be new to Halifax and asked whether the town could regulate where such facilities go. The board was told the town could pursue a bylaw, with the caveat that solar facilities carry some protection under state zoning law.
The pause is meant to give the town time to examine the change and put together a proposed bylaw. The motion was declared unanimous on a voice vote. Announcing the result, the chair said there is a moratorium on the issue for now and the town will defer to counsel for further help.
Jason Desrosier, a senior planner with Old Colony Planning Council, later told the board that battery storage systems are protected under the Dover Amendment and cannot be banned outright, and that, as the planner understood it, moratoriums cannot be placed on facilities allowed under the consolidated process. Temporary moratoriums could apply to larger Tier 2 or Tier 3 battery systems. Asked by a resident whether the motion should be amended to make it temporary, the board member who made the motion said it already was.
Master plan. Desrosier said $50,000 had been secured through a state earmark for a master plan update, with the funds now on hold, and that if the money becomes available the plan would need to be done by the end of June 2027. Master plans typically cost $50,000 to $100,000. He said a housing production plan would likely not qualify for grants because of the town’s status under the MBTA Communities Law, and that an updated master plan could leave zoning out entirely.
Amy Troup, who serves on the Planning Board, speaking as a resident, argued that the state was circumventing private property rights and that new housing would strain the town’s water supply and schools. Board members responded that nothing was being decided that night, and one pledged never to vote to spend the money without the town’s authority.